Measure the slab, then review the work around it.
Separate geometric concrete volume, planning allowance and the wider extension package.
An extension estimate needs more than a single floor-area figure. For a uniform rectangular slab, the concrete quantity depends on length, width and thickness. The work around that slab needs its own scope and measurement basis.
Start with the stated dimensions
Use metres for all three inputs. A drawing thickness of 150 mm is 0.15 m. For an example 10 m × 8 m × 0.15 m slab, the geometric volume is 12 m³. Keep the drawing reference and revision beside the measurement.
The simple example assumes uniform thickness without deductions. Steps, thickened zones, edge details, openings and interfaces with existing construction need a clear measurement treatment. They are not automatically represented by a percentage allowance.
Keep the planning allowance visible
An illustrative 5% allowance changes the quantity to 12.60 m³. The allowance is a planning input, not a specified wastage rate or evidence that the existing construction has been investigated. Mark unresolved information for review with the project team.
Apply an equivalent supply rate
At an illustrative GBP 180/m³, the concrete material subtotal is GBP 2,268. This is not a UK market average, price-book entry or supplier offer. Confirm the required product, quoted unit, order size, validity and supply conditions before comparing quotations.
Complete the surrounding scope
Excavation, preparation, reinforcement, formwork, labour, pumping, testing, equipment, delivery and tax are outside the demo subtotal. Strip-out, access and making good may also form part of the extension or refurbishment package. Confirm the actual inclusions rather than inferring them from the concrete figure.
Changing the example rate from GBP 180 to GBP 200/m³ increases the 12.60 m³ material subtotal from GBP 2,268 to GBP 2,520. The GBP 252 difference explains sensitivity to one input; it is not a future price forecast.