Compare the work included, before comparing the total.
Keep drawings, clarifications, exclusions and preparation work alongside the tender price.
Two tender totals may cover different work. One may include strip-out and making good, another may price only the new finish. Before deciding which total is lower, establish what each offer measures and what services it includes.
Build a document-and-scope register
Record the drawings, specifications, schedules, revisions and clarifications used for the estimate. Identify the work package and its boundaries. If later information changes the quantity or method, make that change visible rather than silently overwriting the basis.
Separate new work from existing-work assumptions
For refurbishment, record retained construction, removal, protection, preparation and making good. Mark what is confirmed, assumed or awaiting review. A contingency figure is not proof that hidden conditions have been surveyed.
Normalise the inclusions
Check who provides materials, labour, equipment, delivery, handling, protection and waste removal. Confirm whether preliminaries or other stated additions are included in a rate or listed separately. Avoid counting the same service twice.
Keep measurement units consistent
A rate per m² of measured surface is not directly comparable with a supply-only box price. A concrete volume is not a floor area. Convert quotations to a consistent comparison basis only after the product and included scope are understood.
Record uncertainty without disguising it
List exclusions and unresolved assumptions clearly. Confirm their treatment with the responsible project parties before a commitment. TB can help organise quantities, editable rates and reviewable assumptions; it does not interpret a contract, certify entitlement or decide whether an offer satisfies the tender requirements.